Saudi Urban Water Demand Reduction
Client Brief
Find the cheapest set of measures that cuts water production by 15%.
Your client is the water utility for a Saudi city of about 2 million people. Almost all of its water is desalinated, which is expensive and energy-intensive. The utility has been asked to cut the volume of water it produces by 15% within five years while still meeting demand.
Saudi context: Saudi Arabia relies heavily on desalination, so every cubic metre saved avoids real energy and cost. Losses in the network (leaks and unbilled use) and high household consumption are both recognised issues; water efficiency is part of national sustainability goals.
All figures are fictional case assumptions. Context notes describe the real Saudi setting qualitatively; no real statistics are quoted.
Additional information: Residential demand = 2m people × 0.26 m³ = 520,000 m³/day. The 15% target = 120,000 m³/day.
Client objective
Client objective: Find the cheapest set of measures that cuts water production by 15%.
Exhibits
Exhibit 1 — Baseline
| Metric | Value |
|---|---|
| Daily water production | 800,000 m³ |
| Non-revenue water (leaks and unbilled) | 25% of production |
| Residential consumption | 260 litres per person per day |
| Cost to produce water | SAR 6 per m³ |
Exhibit 2 — Levers
| Lever | Saving (m³/day) | Cost per m³ saved (SAR) |
|---|---|---|
| Leak reduction (pressure management + pipe replacement) | 64,000 | 1.5 |
| Smart meters + consumption feedback | 41,600 | 2.5 |
| Free water-efficient fixture kits | 26,000 | 1.0 |
| Treated wastewater for landscape irrigation | 15,000 | 4.0 |
QUESTION 1 OF 6
How would you structure the utility's water-demand reduction problem? Set out the analyses needed to compare the measures and explain their order of priority.
Build the issue tree
Break the client’s decision into clear branches, then add the drivers to investigate.
Problem Structuring criteria
- MECE Principle 30%
- Logical Organization 25%
- Relevance to the Problem 20%
- Depth of Analysis 15%
- Prioritization of Key Drivers 10%
2 branches · 0 sub-drivers
Submit every step to unlock this tab.

