Client Brief

Cut the mine's emissions by 25% within four years at the lowest net cost, using options that can be delivered in time.

Your client operates an open-pit mine in the Tabuk region. Its emissions come mainly from diesel haul trucks and from diesel generators that power the processing plant, which is far from the grid. The parent company has committed to cut the mine's emissions by 25% within four years and wants a plan that uses evidence on cost, impact and how quickly each option can be delivered.

Saudi context: The Tabuk region has strong sunshine and large open land, which suits solar power. Remote mine sites often run on diesel because grid connections are far away. Mining is a growing sector in the Kingdom's economic diversification plans.

All figures are fictional case assumptions. Context notes describe the real Saudi setting qualitatively; no real statistics are quoted.

Client objective

Client objective: Cut the mine's emissions by 25% within four years at the lowest net cost, using options that can be delivered in time.

Exhibits

Exhibit 1 — Emissions baseline (tonnes CO₂ a year)

SourceTonnes
Diesel haul trucks90,000
Diesel generators for the processing plant45,000
Explosives and other15,000
Total150,000

Exhibit 2 — Abatement options

OptionTonnes cut a yearNet cost per tonne (SAR; negative = saves money)Time to deliver
Haul-road and payload optimisation9,000−606 months
Solar plant with batteries replacing diesel generators30,000+2018 months
Electric trolley-assist for haul trucks25,000+1503–4 years; needs a grid connection
10% biodiesel blend9,000+220Fuel supply limited

Structuring

Build the issue tree

Break the client’s decision into clear branches, then add the drivers to investigate.

Problem Structuring criteria

  • MECE Principle 30%
  • Logical Organization 25%
  • Relevance to the Problem 20%
  • Depth of Analysis 15%
  • Prioritization of Key Drivers 10%