Beginner multiple-choice cases
The new catalog contains 20 beginner multiple-choice cases and 95 essay cases.
Difficulty:Easy
Choose a multiple-choice case
São Paulo Manufacturing Supply Chain Resilience
Cut the cost of late steel deliveries at the lowest annual cost.
Read case details and exhibits
Tables and data
| Item | Value |
|---|---|
| Steel coil used | 2,000 tonnes a month (about 462 tonnes a week) |
| Steel price | USD 900 per tonne |
| Late deliveries last year | 3, each about 2 weeks late |
| Production lost during a late delivery | About half of output |
| Lost margin per week of full stoppage | USD 400,000 |
| Option | Effect | Cost |
|---|---|---|
| A. Hold 2 more weeks of coil (4 weeks in total) | Avoids about 80% of the lost production | Holding cost 20% of extra stock value a year |
| B. Buy 30% of coil from a second mill | Avoids about 50% of the lost production | Second mill charges 4% more |
Your client
Your client is a São Paulo manufacturer of steel shelving and storage racks. It buys all its steel coil from a single steel mill, with a 6-week lead time, and keeps about 2 weeks of coil in stock. Three times last year the mill delivered about two weeks late, and the plant had to stop some lines. The operations director asks how to make supply more reliable at sensible cost.
What changed?
All numerical data in this case are fictional case assumptions.
Client objective
Client objective: Cut the cost of late steel deliveries at the lowest annual cost.